- BUILDING THE VISION … FULFILLING OUR
MISSION -
Purpose of Expansion
With pressure to expand and enhance the facility at Pine Summit, the board hired an architectural company, who is highly specialized in developing camps nationwide, to create a Master Plan for Expansion in 1999. Building the Vision is a 10-year, $29 million, capital improvement plan that will:
|
Phase 1 - $2,995,800
|
|
|
· Construct Summit Village Lodge #1 (adult, hotel-style suites)
|
Complete (10/05)
|
|
· Construct Summit Village Lodge #2 (adult, hotel-style suites)
|
Complete (01/06)
|
|
· Add artificial grass to recreation field
|
81,000
|
|
· Reconstruct vehicle paths & add lighting
|
207,000
|
|
· RV Park
|
Complete (07/05)
|
|
|
- Build retainer walls in RV Park
|
4,900
|
|
|
- Add post lamps in RV Park
|
2,900
|
|
· Village Lodges Landscaping
|
19,000
|
|
· (2) Mini-Buses
|
81,000
|
|
· Construct Summit Village Lodge #3 (adult, hotel-style suites)
|
2,600,000
|
|
Phase 1 Total:
|
$2,995,800
|
|
Phase 2 - $10,439,700
|
|
|
· Build Maintenance/Accommodations Building
|
|
|
|
- Construct new
Maintenance
Building
|
$311,000
|
|
|
-
Construct
Storage
Building
|
$149,000
|
| |