Purpose of Expansion


With pressure to expand and enhance the facility at Pine Summit, the board hired an architectural company, who is highly specialized in developing camps nationwide, to create a Master Plan for Expansion in 1999. Building the Vision is a 10-year, $29 million, capital improvement plan that will:

Phase 1 - $2,995,800

 

·  Construct Summit Village Lodge #1 (adult, hotel-style suites)

Complete (10/05)

·  Construct Summit Village Lodge #2 (adult, hotel-style suites)

Complete (01/06)

·  Add artificial grass to recreation field

81,000

·  Reconstruct vehicle paths & add lighting

207,000

·  RV Park

Complete (07/05)

 

- Build retainer walls in RV Park

4,900

 

- Add post lamps in RV Park

2,900

·  Village Lodges Landscaping

19,000

·  (2) Mini-Buses

81,000

·  Construct Summit Village Lodge #3 (adult, hotel-style suites)

2,600,000

Phase 1 Total:

$2,995,800

Phase 2 - $10,439,700

 

·  Build Maintenance/Accommodations Building

 

 

- Construct new Maintenance Building

$311,000

 

- Construct Storage Building

$149,000

 

 